Diesel climbs, trade rates hold
Diesel prices kept climbing in October, but the cost of building hasn’t followed them up. Stats NZ says diesel rose 11.1% in October and petrol 11.9%, the third monthly rise in a row.
“Petrol prices have increased 40.8% since February 2026, while diesel prices have increased 73.6%,” Stats NZ prices and deflators spokesperson Jason Attewell said.
Earthmoving feels it first
QV CostBuilder’s latest cost update, published on 29 October, found the diesel prices it tracks had risen by an average of 19% in a month and were 76.2% higher than in February. The two figures use different measures and periods, but they point the same way.
The jobs that burn the most diesel have moved first. QV found excavation rates up 3.9% in a month, while piling and demolition rates both rose 0.6%.
Across the wider sector, the effect has been small so far. QV’s update tracked more than 7,000 data changes across Auckland, Wellington, Christchurch, Dunedin, Hamilton and Palmerston North, and average trade rates rose just 0.1%, with rises and falls across products and trades largely cancelling out.
“What won’t surprise anyone who’s had to fill up their truck recently is that diesel has moved sharply higher again. This hasn’t directly translated into broad-based construction cost inflation,” QV CostBuilder quantity surveyor Martin Bisset said. “We’re seeing that pressure most clearly in the parts of the job that use the most fuel, while many other material and trade rates have moved much more modestly overall.”
Which materials are moving
Some materials are rising faster than others. QV found processed timber products up 6.2%, medium-density fibreboard up 2.8%, reinforcing up 2.7%, roofing and cladding up 1.6%, and insulation up 1.1%.
Others fell. Adhesives and sealants dropped 4.2%, kitchen-related costs fell 1.2%, and structural timber slipped 0.2%.
“The overall picture is relatively steady, but that doesn’t mean every part of a build is standing still. Where your costs will move most depends heavily on what you’re building, what materials you need, and how exposed the job is to fuel,” Bisset said.
Where to put the contingency
For contractors pricing work now, the figures show where cost risk sits. Earthworks, excavation and any job heavy on machine hours and cartage are the most exposed to further fuel rises, while most trade rates have barely moved.
Quotes for civil and earthworks jobs that run into 2027 need a clear position on fuel. That can mean a fuel adjustment clause, a shorter validity period on the quote, or a contingency sized to the job’s machine hours and cartage distances.
On the materials side, timber products, MDF and reinforcing have moved the most in QV’s latest update. Contractors locking in prices for jobs with large timber or reinforcing packages can protect themselves by confirming supplier prices close to ordering, or agreeing how price changes are shared.
Subcontractors on fixed-price work carry the risk of rising fuel costs unless their contract says otherwise. Checking whether a head contract includes price adjustment provisions, and whether they flow down to subcontracts, is worth doing before signing.
Stats NZ’s next monthly fuel figures will show whether the run of price rises has continued.
QV CostBuilder updates its construction costs monthly, and Stats NZ publishes fuel prices each month as part of its selected price indexes.