Main construction has started on Wairoa’s North Clyde floodway, the centrepiece of a $70 million Crown-funded flood protection project. Hawke’s Bay Regional Council (HBRC) describes it as “the largest infrastructure investment Wairoa has seen in decades”.

The floodway will be 1.1km long and 190m wide. It’s designed to protect 586 properties in North Clyde that were classed as Category 2C after Cyclone Gabrielle, to a 1% annual exceedance probability flood standard, meaning a flood with a 1% chance of happening in any year.

Local Democracy Reporting put the start of main works, marked with a karakia, on Monday 16 November.

Local contractor, staged works

HBRC appointed Goodman Contractors through an early contractor involvement process, “with a focus on local contractors and supply chains”. Goodman has been on site since early 2026, starting with tree clearing.

Enabling works began in August, covering demolition, site set-up and a temporary haul road between Waihirere Road and Ruataniwha Road, on land provided by Tātau Tātau o Te Wairoa. The first stage of main works is the town-side stopbank, along with stormwater and drainage.

Every contractor on site completes a cultural, archaeological, ecological and environmental induction, and marae cultural monitors stay on site throughout the build. Main construction is due to finish in late 2027.

“From here, the focus is simple – build it well, build it safely, and get it done,” Crown Manager Lawrence Yule said.

Nearly 40 years in the making

“Wairoa has been waiting for this for nearly forty years, since Cyclone Bola showed just how vulnerable the town was to flooding,” HBRC Chair Sophie Siers said.

Wairoa Mayor Craig Little said, “Seeing machinery on the ground and the floodway taking shape gives people something real to hold on to.”

Not everything is funded yet. A training groyne at the river mouth is still being investigated and “is not yet funded”, HBRC says, and modelling of the upper catchment is due by the end of the year.

HBRC hasn’t released the value of Goodman’s contract within the $70 million project.

More flood work in the region

The Wairoa job is part of a wider run of flood protection work in Hawke’s Bay. In early November, HBRC announced construction starting on a stopbank upgrade at Waipawa, part of a $30 million regional stopbank programme.

That job raises 3km of stopbank by anything from a few centimetres to 2m, runs until autumn 2027, and reuses about 60,000 cubic metres of river gravel. Together, the two projects mean steady civil work in the region through 2027.

Earthworks, drainage, stopbank construction and haulage are the main trades on these jobs, alongside the cultural and environmental monitoring now standard on flood projects in the region. Contractors wanting work on future stages should keep an eye on HBRC’s procurement notices as the river-mouth and upper-catchment work is scoped.